Timeline:
2021 - Pole building, utilities and piping installed. Screw press expected to be online in May.
2020 - A pole building structure and covered pad will be constructed to house the equipment and dewatered sludge. The screw press is expected to be online in 2021.
2019 - FKC was selected to provide the screw press for the dewatering process. The equipment was delivered to the Wastewater Treatment Plant.
2018 - The City advertised for a sludge dewatering screw press.
2015-2017 - Operators at the WWTP pilot a screw press, and additional dewatering systems.