Storm Water Projects

Olson Ditch Bank Stabilization Improvements

  • Project Number: 887 Olson Ditch Improvements
  • Project Description: Olson Ditch storm water improvements to stop erosion
  • Status: Land survey and design completed
  • Engineer for drafting: Firwood Design Group
  • Requirements: Approved permits from Army Corps of Engineers and Department of State Lands received July 2016
  • Contractor:  Paragon Construction
  • Schedule: Work began in August of 2016 and final planting is scheduled for December 
  • City Contact: John Cramer, Senior Engineer, 503-874-2209


Lincoln Street Stormwater Drainage Improvements

  • Project Number: 932
  • Project Description: Storm water drainage improvements along Lincoln Street from N 2nd to Mill Street
  • Design: In progress
  • Engineer:  Keller Associates
  • Contractor:  TBD
  • Schedule: Design 2016/17 and Construction 2017/18
  • City Contact: John Cramer, Senior Engineer, 503-874-2209