Street Projects

​McClaine Street Reconstruction

Project Description

McClaine Street between Main Street (southern extent) and C Street (northern extent) has exceeded its useful life and requires reconstruction. Reconstruction of the right-of-way (ROW) will include a new road surface, storm drainage, larger sewer pipe, new sidewalks, and bike lanes. 
The estimated cost for final engineering and construction is $5.1 million. The initial estimate for underground utilities is $1 million, for a total project cost of $6.1 million. The adopted Fiscal Year 2019/2020 Budget includes $4.3 million for Final Design and construction. It is likely that the funding gap will require public financing which will be addressed when the Final Design is completed this fall.

McClaine Street Preliminary Design

Timeline

  •  July 2018 - Public Works contracted with Keller Associates for pre-design of McClaine Street Reconstruction project for $49,950.
  • February 2019 - Two conceptual designs were presented to City Council. 
  • March 2019 - City Council directed the consulting engineering firm to develop a third concept that included no bike lanes and eight foot sidewalks on both sides of the street.
  • April 2019 - City Council made an amendment to the preferred alternative adding bike lanes to both sides of the street for the final design process.
  • May 23, 2019 - The Request for Proposal for Final Design closed. The sole responder was Keller Associates.
  • June 2019 - Keller Associates was awarded the Final Design contract for $353,300.
  • July 2019 - Public Works will patch sections of the eastbound travel lane from W. Main Street to Phelps Street and several areas of the westbound travel lane from Phelps Street to W. Main Street.