CIPP (Cured-in-Place Pipe) Project

cipp

CIPP (Cured-in-Place Pipe) Project

Phase 1- Completed cleaning and TV inspection of selected mains to be lined on N. Water St. & E. Main St.

Phase 2 – Install new sewer mainline liner.

  • All homeowners will be notified by the City of Silverton and Insituform prior to work beginning.  
  • Work will begin Wednesday, February 21, 2024, and an estimated completion date of February 29, 2024.
  •  The sewer mainlines to be lined are listed below, and the following dates are tentative.
    • Brooks St., Wednesday, February 21, 2024
    • Alder Ave., Thursday, February 22, 2024
    • Sherman St., Friday, February 23, 2024
    • Main St., Monday, February 26, 2024 & Wednesday, February 28, 2024
    • Jerome St. Monday, February 26, 2024 & Tuesday, February 27, 2024
    • Oak St. Thursday, February 29, 2024