System Development Charge Methodology Updated 07-01-2023

System Development Charges (SDCs) 

SDCs are a one time charge for new development. These fees are designed to recover the costs of infrastructure capacity needed to serve new development. Based on the State of Oregon Statute ORS 223.304, the charges are broken down into three components: 1) Reimbursement to recover existing facility capacity available for growth; 2) Improvement to recover planned capacity improvements for growth; and 3) Administration to recover direct costs. 

All SDC fees will be adjusted annually on July 1 to account for changes in the costs acquiring and constructing facilities. The adjustment factor is based on the change in construction costs according to the Engineering News Record (ENR) Northwest (Seattle, Washington) Construction Cost Index (CCI) from December to December. The rates for SDCs have been increased by the change December 2021 to December 2022. 

To access a custom SDC generator click here. 

Scalable SDCs for Single Family Homes

The Scalable System Development Charges for Single Family Homes applies based on the living area of a single family home. "Living area"  means the habitable floor area of a residential structure conforming to applicable building codes; typically this does not include the garage area, attic and/or basement areas, with substandard ceiling height or substandard egress. 

Water SDC Schedule
Water SDC Schedule for a Single Family Home
Square Feet
Fixture Units
Reimbursement SDC
Improvement SDC
Total SDC 
Starting SDC per Single Family residence 
644
17.0000
$ 1231.63
$ 6,287.49
$ 7,519.12
SDC Per Square Foot of a Single Family Residence 
1
0.0043
$ 0.31
$ 1.57
$ 1.88
Maximum SDC per Single Family Residence 
3,648
29.7887
$ 2,158.16
$ 11,017.43
$13,175.59

 

Wastewater SDC Schedule
Wastewater SDC Schedule for a Single Family Home 
Square Feet
Residents 
Reimbursement SDC
Improvement SDC
Total SDC 
Starting SDC per Single Family Residence 
644
1.0000
$ 627.29
$ 1,296.92
$1,924.21
SDC per square foot of Single Family Residence 
1
0.0016
$ 0.97
$ 2.02
$ 2.99
Maximum SDC per Single Family Residence 
2,605
4.0475
$ 2,539.00
$ 5,249.34
$7,788.34
Transportation SDC Schedule
Transportation SDC Schedule for a Single Family Home 
Square Feet 
Residents 
Reimbursement SDC
Improvement SDC
Total SDC 
Starting SDC per Single Family residence
644
1.0000
$ 245.64
$ 1,213.03
$1,458.67
SDC per Square foot of Single Family Residence 
1
0.0016
$ .038
$ 1.89
$ 2.27
Maximum SDC per Single Family Residence 
2,605
4.0475
$ 994.24
$ 4,909.79
$5,904.03
Parks SDC Schedule
Parks SDC Schedule for a Single Family Home 
Square Feet 
Residents
Reimbursement SDC
Improvement SDC
Total SDC
Starting SDC per Single Family Residence 
644 1.0000   $ 2,420.73 $2,420.73
SDC per Square Foot of Single Family Residence 
1 0.0016   $3.76 $3.76
Maximum SDC per Single Family Residence 
2,605 4.0475   $ 9,798.04 $ 9,798.04
Stormwater SDC Schedule
Stormwater SDC Schedule for a Single Family Home 
   
Reimbursement SDC
Improvement SDC
Total SDC
Per Square Foot 
 
 
$ 0.1618
$ 0.1400
$0.3018

Additions to Single Family Homes 

Additions to Single Family Homes, including Accessory Dwelling Units are not exempt from System Development Charges. The above SDC per square foot applies to additions and ADUs where the resulting living area exceeds 1,834 square feet. Any square footage over 1,834 would incur the SDCs on a per square foot basis per the above tables for all SDCs. 

Non-Scalable SDCs for all other System Development Charges

Water SDCs
Meter Size
Reimbursement Fee
Improvement & Administrative Fee
Total Fee
3/4"
$ 1,499.00
$7,655.00
$9,154.00
1"
$2,498.00
$ 12,759.00
$ 15,257.00
1.5"
$ 4,997.00
$25,520.00
$ 30,517.00
2"
$ 7,995.00
$40,832.00
$48,827.00
3"
$14,990.00
$76,559.00
$91,549.00
4"
$24,985.00
$ 127,598.00
$ 152,583.00
6"
$49,969.00
$ 255,195.00
$ 305,164.00
8"
$79,951.00
$ 408,312.00
$ 488,263.00
Wastewater SDCs
Meter Size 
Reimbursement Fee
Improvement & Administrative Fee
Total Fee 
5/8" & 3/4"
$ 1,679.00
$3,465.00
$5,144.00
1"
$ 2,795.00
$ 5,776.00
$ 8,570.00
1.5"
$ 5,589.00
$ 11,552.00
$ 17,141.00
2"
$ 8,943.00
$ 18,481.00
$ 27, 424.00
3"
$ 17,884.00
$ 36,964.00
$ 54,849.00
4"
$ 27,945.00
$ 57,756.00
$ 85,702.00
6"
$ 55,890.00
$ 115,521.00
$ 171,402.00
8"
$ 89,424.00
$ 184,820.00
$ 274,244.00
10"
$139,725.00
$ 288,782.00
$ 428,507.00
12"
$ 241, 445.00
$ 499,015.00
$ 740,459.00
Stormwater SDCs
Meter Size
Reimbursement Fee
Improvement & Administrative Fee
Total Fee
Per EDU
$ 505.00
$464.00
$ 969.00
Per Sq. Ft.
$ 0.1618
$ 0.1400
$ 0.3018

 

Parks SDCs
Customer Classification Number of Dwelling Units  Reimbursement Fee Improvement Fee Total Fee
Multi-Family Dwelling Unit 
1
$0
$4,287.00
$4,287.00
Duplex
2
$0
$ 8,575.00
$8,575.00
Triplex
3
$0
$ 12,862.00
$12,862.00
Four-plex
4
$0
$ 17,150.00
$17,150.00
Apartment Complex
*
*
*
*
Condominium Complex 
*
*
*
*
Retirement/Assisted Living Complex 
*
*
*
*
Business- FTE
-
*
$92.00
$ 92.00

*Multiply the number of dwelling units by the corresponding detached multi-family per dwelling fee component. 

Transportation SDCs
Land Use* Improvement Fee Reimbursement Fee Compliance Total Fee
Apartment
$ 2,020.00
$ 433.00
$ 123.00
$2,576.00
General Office Building 
$ 4,854.00
$ 1,042.00
$ 295.00
$6,191.00
General Light Industrial 
$ 3,160.00
$ 678.00
$ 192.00
$4,030.00
High-Turnover (sit down restaurant)
$ 12,755.00
$ 2,738.00
$ 775.00
$16,268.00

 

*These are the most common land-use applications; for a complete list of the ITE codes, contact the Community Development Department.